Reconstruction of Swa Creek and Dokhtawaddy bridges remains unfinished after 20 months

Phyo/Pearl (NP News) - November 23

The construction of the Swa Creek Bridge and Dokhtawaddy Bridge on the expressway remains incomplete more than 20 months after they were damaged in the Mandalay earthquake, a source close to the bridge construction told The Statesman Journal.
Following the collapse of both the inbound (Mandalay-to-Yangon) and outbound (Yangon-to-Mandalay) spans of the Swa Creek Bridge on the Yangon-Mandalay Expressway due to the major Mandalay earthquake on March 28, 2025, reconstruction work was initiated. It is reported that the rebuilding of the inbound span (Mandalay-to-Yangon) reached 100 percent completion around last June.
Currently, construction on the outbound span of the Swa Creek Bridge is approximately 50 percent complete. While efforts are underway to finish the project within the current fiscal year, its timely completion remains uncertain.
“The Swa Creek Bridge is being completed within this budget. But officially, we have not received the full funding. We are just working on it in the meantime. We are working on opening it in 2027. More than 50 percent is already completed,” the source told The Statesman.
Similarly, reconstruction of the Dokhtawaddy Bridge at Milepost 358 on the Yangon-Mandalay Expressway, also damaged in the Mandalay earthquake, had been scheduled for reopening by the end of this year. However, due to several challenges, the project is now expected to be completed in March 2027.
“We are also working to complete the Myitnge (Dokhtawaddy) Bridge within this fiscal year, and it looks certain to be finished on time. Originally, we projected a December completion for it, but we have now set an internal departmental target to finish it by February. One of the river piers got submerged, leaving the section that needed to be concreted underwater—mainly due to heavy rainfall. We will definitely complete and open the bridge within this budget year," he said. –

Reconstruction of Swa Creek and Dokhtawaddy bridges remains unfinished after 20 months
Phyo/Pearl (NP News) - November 23
The construction of the Swa Creek Bridge and Dokhtawaddy Bridge on the expressway remains incomplete more than 20 months after they were damaged in the Mandalay earthquake, a source close to the bridge construction told The Statesman Journal.
Following the collapse of both the inbound (Mandalay-to-Yangon) and outbound (Yangon-to-Mandalay) spans of the Swa Creek Bridge on the Yangon-Mandalay Expressway due to the major Mandalay earthquake on March 28, 2025, reconstruction work was initiated. It is reported that the rebuilding of the inbound span (Mandalay-to-Yangon) reached 100 percent completion around last June.
Currently, construction on the outbound span of the Swa Creek Bridge is approximately 50 percent complete. While efforts are underway to finish the project within the current fiscal year, its timely completion remains uncertain.
“The Swa Creek Bridge is being completed within this budget. But officially, we have not received the full funding. We are just working on it in the meantime. We are working on opening it in 2027. More than 50 percent is already completed,” the source told The Statesman.
Similarly, reconstruction of the Dokhtawaddy Bridge at Milepost 358 on the Yangon-Mandalay Expressway, also damaged in the Mandalay earthquake, had been scheduled for reopening by the end of this year. However, due to several challenges, the project is now expected to be completed in March 2027.
“We are also working to complete the Myitnge (Dokhtawaddy) Bridge within this fiscal year, and it looks certain to be finished on time. Originally, we projected a December completion for it, but we have now set an internal departmental target to finish it by February. One of the river piers got submerged, leaving the section that needed to be concreted underwater—mainly due to heavy rainfall. We will definitely complete and open the bridge within this budget year," he said. –